Automotive & mobility 2024 24 weeks

Brendalen Special Vehicles

Niche vehicle manufacturer, three platforms, one new launch per year

Engagement
24 weeks
Office
Munich
Lead partner
Katharina Brandt

The challenge

Brendalen's launches were famous for slipping: the last three took 41, 44, and 39 weeks from design freeze to stable rate, each slip burning working capital and dealer patience.

What we did

Katharina's team rebuilt the NPI gates with named entry and exit criteria, brought the two key suppliers into design review two, and staffed the pilot build with the production crew on the production calendar.

A single release calendar now governs engineering, purchasing, and the plant; gate skips require a logged decision from the program board, which meets weekly for forty minutes.

The outcome

The next launch reached stable rate in 19 weeks from design freeze — less than half the recent average — with first-pass yield at 97 percent by week four of ramp.

Impact metrics

Design freeze to stable rate −22 weeks

Before 41 weeks
After 19 weeks

First-pass yield at ramp week 4 +13%

Before 84 %
After 97 %

Late engineering changes −31 count

Before 37 count
After 6 count

Bars are scaled per metric against its own maximum. Direction of improvement: Design freeze to stable rate, First-pass yield at ramp week 4, Late engineering changes — see each metric.

Expertise behind this program

Facing something similar?

Describe your baseline and target. If we have run it, we will say so — and show you the number.