Scrap almost always comes from three sources
After eleven yield programs we can predict the shortlist before the first shift is measured: furnace practice on product changes, handling between processes, and a maintenance calendar that slips under production pressure. Together they explain most of the gap between nameplate and shipped tonnes.
The discipline is valuing each at the month's actual selling price, so the plant fixes the expensive one first instead of the familiar one.